Planning for water safety in buildings and workplaces
Contents |
[edit] Introduction
Water systems are present in almost every building. These typically include domestic water systems (which provide potable hot and cold water) and central heating systems.
Some buildings also have chilled water systems to provide space cooling. Central heating and chilled water systems are often referred to as closed loop systems.
Some buildings also have decorative water features such as fountains and industrial features such as vehicle washing facilities, landscape watering, and leisure facilities such as pools and spas. Additionally, water systems may be installed or brought into the building by users, for example drinking water dispensers and humidifiers.
Owners and operators of such buildings should have a plan to ensure all these water systems are safe for the users, including visitors, employees and contractors.
[edit] A holistic approach to water safety
In 2011, the World Health Organization (WHO) published Water Safety in Buildings. This publication offers guidance specific to water safety in buildings with the adoption of water safety planning.
The document recommends three components in the development of a water safety plan:
- Assessing the system to determine whether the provider as a whole can deliver water of a sufficient quality.
- Monitoring control measures in the supply chain that are of particular importance in securing water safety.
- Adopting a management approach that describes the actions to be undertaken from normal conditions to extreme events and relays how they will be communicated to the various stakeholders.
[edit] BS 8680:2020
Each of these three components were integrated into a British Standard, BS 8680:2020 Water quality. Water safety plans. Code of practice. The standard was published in May 2020.
This code of practice follows the aforementioned WHO guidance and integrates some specificities encountered in the UK legislation and regulations (and therefore goes beyond the simple legionella risk assessment encountered in most buildings and workplaces). It looks at all water systems, assessing their risk, monitoring the identified mitigation measures for these risks and outlining the implementation of an adequate management scheme.
[edit] Water Safety Plan (WSP) and Water Safety Group (WSG)
The code of practice is wrapped up into a Water Safety Plan (WSP) supported by a Water Safety Group (WSG). This approach holistically covers the entire lifespan of a building from its conception and design up to its alteration or decommissioning.
A water safety plan can be developed by carrying out three key steps:
- Assessing the water systems. What systems are present? Where are they? Who uses them?
- Monitoring the control measures. How to monitor? When to inspect?
- Managing with adequate communication. Who is responsible? What decisions are made?
To sustain this plan would require suitable people to be involved during these various steps. These people would form part of the water safety group. Some people may take part permanently due to their level of responsibility associated with the water systems (for example the building owner) and some may take part only occasionally (for example external consultants or water experts).
[edit] Water system failures
We often investigate water system failures that could have been prevented or their catastrophic consequences mitigated by an adequate WSP supporting by a WSG.
Failures are often encountered in a building during the first couple of years of operation. The operation team or building owner blames the design and construction team for the failures, and the design and construction team blames the operator or owner for not having correctly run and maintained the systems in their early life. Clearly all these parties should take part in the WSG and work together in producing a realistic WSP, otherwise it is a recipe for disaster!
One element the BS 8680 code of practice recommends for improving collaboration between various parties and stakeholders is the use of a Soft Landings approach. The BSRIA Soft Landings Framework can be found in the guidance document BG 54/2018 which is free to download to all members on the BSRIA website.
This approach will assist project teams, clients and building owners in the development of a WSP, identification of persons to include in a WSG and emphasises the importance of a planned handover when the building is completed.
Another element the BS 8680 code of practice stresses in the development of a successful WSP is to focus not solely on drinking water quality but also on the overall safety of other water systems in a building.
For instance, a lack of heating in a public place may result in visitors being unable to attend during the winter period (and resulting in reputation damage). Another problem could be a lack of cooling, which may be critical to industrial units (and may have negative consequences related to their safe operation). Both examples ultimately have a financial impact on the business activity either directly (the industrial unit having to stop) or indirectly (the public not visiting shops/retailers).
As with any plan, if it is not correctly prepared by competent people, it is likely to fail, possibly with severe consequences. This is why it is important to have a trail to follow and also to have suitable guidance to help avoid pitfalls.
Therefore, it is essential to first define what is to be achieved by having a water safety plan: Is it a business objective? A compliance requirement? A strategic positioning on the market?
The next step would be to develop the plan, involving the relevant people by following the key steps of the code of practice.
Finally, the success of the WSP should be regularly evaluated, members of the WSG should be rewarded for their effort and the whole process should be reviewed for improvements. In other words, it is advisable to follow the process defined in BG 74/2019 Success Criteria for Soft Landings Projects.
This article originally appeared on the BSRIA website. It was written by Martin Ronceray BSRIA Engineering Investigations Lead and published in July 2020.
--BSRIA
[edit] Related articles on Designing Buildings
- Back to the workplace: are you prepared?
- BS 8680:2020 Water quality. Water Safety Plans. Code of practice.
- BSRIA articles on Designing Buildings Wiki.
- Building performance evaluation.
- Commissioning building systems.
- Defects liability period.
- Drinking water quality.
- Soft landings.
- Soft landings and business-focused maintenance.
- Soft Landings for owners.
- Water.
- Water safety plan WSP.
[edit] External resources
- British Standard BS 8680:2020 Water quality. Water safety plans. Code of practice.
- BSRIA Guide BG 74/2019 Success Criteria for Soft Landings Projects.
- BSRIA Guide BG 29/2020 Pre-Commission Cleaning of Pipework Systems 6th edition.
- BSRIA Guide BG 50/2013 Water Treatment for Closed Heating and Cooling Systems.
- BSRIA Guide BG 33/2014 Illustrated Guide to Hot and Cold Water Services.
- BSRIA Guide BG 53/2016 Business-Focused Maintenance.
- BSRIA Guide BG 54/2018 Soft Landings Framework 2018.
- BSRIA Guide BG 57/2015 Legionnaires' Disease - Risk Assessment.
- BSRIA Guide BG 58/2015 Legionnaires' Disease - Operation and Maintenance Log Book.
- BSRIA Guide BG 2/2010 Commissioning Water Systems.
- World Health Organization, Water safety in buildings, March 2011.
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).